Bayside Academy

OWNER
Bayside Academy
HPM SERVICES
Project Management

Bayside Academy engaged HPM to provide Project Management and Planning Services for new facilities on its campus in Daphne, Alabama. HPM supported the completion of Bayside Academy’s new middle school, a 21,400-square-foot, two-story building complemented by a 57-space parking lot. The project expanded the campus to better serve students and faculty while aligning with the school’s long-term operational and budget goals.
HPM joined the project midway through construction, transitioning project oversight from a board-led effort to a dedicated professional management approach. Upon engagement, HPM assumed responsibility for schedule reviews, invoice and change order evaluations, and weekly site walks to monitor progress, coordinate stakeholders, and maintain project momentum through completion.
Early in HPM’s involvement, the project faced a complex civil engineering challenge related to parking lot grading and stormwater drainage. Multiple design options had been explored prior to HPM’s arrival without resolution. HPM collaborated closely with Bayside Academy to define priorities, then worked with the civil engineer through several design iterations to align scope, constructability, and budget. HPM coordinated with the contractor to communicate revisions to the City of Daphne and adjust the construction schedule to mitigate delays. In addition, HPM engaged the landscape designer to review the updated civil plans and ensure compliance with municipal requirements for trees and plantings.
Beyond the original scope, HPM provided leadership in furniture procurement for non-classroom spaces after the owner determined the architect’s selections exceeded the project budget. HPM developed a tracking system to ensure all spaces—including exterior porches, conference rooms, administrative offices, lobby, counseling areas, and staff workrooms—were appropriately furnished. HPM also coordinated multiple furniture moving vendors to streamline logistics and ensure a smooth, efficient transition into the new facility.

Ready to discuss your next project?